2023

Building completion

2022

Commissioning

2020

September: Topping-out ceremony

2018

October: Break-ground

2018

March: Building permission and clearing the construction site

2017

September: Start of construction licensing procedure

2017

April: Start of detailed planning

2016

November: Completion of construction documents

2015

October: Jury

2015

April: Launch of the competition

2015

January: Construction workshop for the staff of the Department of

2014

December: Announcement of a Europe-wide competition

2014

October: Board resolution of the Medical Center – University of

2014

September: The Ministry of Finance gives consent to the construction

2014

Formal request of consent to the Ministry of Finance

2014

The board of directors of the Medical Center – University

2014

Completion of the qualitative room and function program 3.0 according

2014

Development of the qualitative room book in collaboration with KopVol

2013

Development of guiding principles

2013

Planning of the room and function program 2.0

2012

Workshop: room and function program 1.0

2012

The Ministry of Finance issues a mandate to plan and

2012

Founding of INITIATIVE für Unsere Kinder- und Jugendklinik Freiburg e.V.

2009

User requirement

2008

Feasibility analysis

2006

Crash-Report